'Series of tests' behind power outages on Abaco

By NICO SCAVELLA

Tribune Staff Reporter

nscavella@tribunemedia.net

THE recent wave of power outages in Abaco were the result of "a series of tests" at Bahamas Power & Light's Wilson City Power Station, the utility provider said.

BPL, in a statement on Friday, said it was "necessary" to conduct the tests as it seeks to "improve our reliability and system stability."

BPL acknowledged that those tests resulted in "a number of repeated power outages on the island over the past ten days."

The statement by BPL comes just days after one hotelier told The Tribune that the repeated outages have turned potential visitors away.

Molly McIntosh, general manager of the Bluff House Beach Resort and Marina, said while the situation has become better since the July 7 holiday weekend, the power was "still going off for an hour or so every other day."

Additionally, one visitor, after seeing The Tribune’s articles online, contacted this newspaper and complained that the outages were the worst his family had seen since visiting the Abacos from the early 1970s.

BPL, in a statement last month, acknowledged it was having challenges with its generation and distribution network in Abaco, adding that copper theft continues to be a "significant problem" responsible for a number of prolonged outages.

The company said it was working constantly to resolve issues responsible for the recent periods of supply interruption.

"BPL sincerely apologizes to its customers for the inconvenience caused during this time and remains committed to the continuous improvement of service to the island," BPL's statement on Friday said.

Last month, BPL blamed "copper theft" and "distribution challenges" for the constant power outages that have plagued Abaco.

At the time, Bahamas Electrical Workers Union (BEWU) President Paul Maynard called the frequent power outages in Abaco "disgraceful" and "unacceptable." He urged BPL to "overhaul the island's protection system", which he claimed has not been upgraded in 25 years.

Abaco residents also expressed their disgust on BPL's Facebook page, with some persons calling for a march to Parliament against the company.

Also last month, Works Minister Desmond Bannister said he has "serious concerns" with BPL's ability to "keep the lights on this summer."

At the time, Mr Bannister said he is already "looking to find new, alternative ways" of producing energy, including solar.

Comments

alfalfa says...

Would it not be normal to advise consumers of the tests beforehand, as well as the times of same and the length of outages that could be expected? A slipshod operation, for sure.

Posted 5 August 2017, 9:15 a.m. Suggest removal

avidreader says...

An interesting idea but "The Abaconian" newspaper only appears twice a month with those all- important real estate advertisements in full colour so it will not be as convenient as it used to be in Cuba when the party newspaper "Granma" was in the habit of printing Horarios de Apagones (a schedule of power cuts) so as to forewarn the populace.

Posted 5 August 2017, 9:22 a.m. Suggest removal

sheeprunner12 says...

The Abaco BPL plant is less than 10 years old ....... what is their excuses for power cuts????
Long Island BunkerC power plant is 25 years old and it rarely has unscheduled power cuts ..... It all starts with management, dedication and planning

Posted 5 August 2017, 10:44 a.m. Suggest removal

baldbeardedbahamian says...

I have been told that the problem is not just the lack of maintenance of the plant itself but also the infrastructure to distribute the power, the cables are old or not of sufficient capacity to handle the load.
The maintenance problem is fixable more easily than the cable problem which will require a significant investment.

Posted 5 August 2017, 11:52 a.m. Suggest removal

DDK says...

I believe you have just hit the nail on the head! We should get rid of Power Secure and put some of that give-away money towards upgrading the distribution cables.

Posted 5 August 2017, 1:04 p.m. Suggest removal

alfalfa says...

Avidreader, they have the Tribune, Guardian, Punch, Cable, and radio to broadcast these fictituous "test" schedules on. And the Abaconian if they so desire.

Posted 5 August 2017, 2:47 p.m. Suggest removal

The_Oracle says...

Testing what happens if you let the engines run out of oil?
That is believable. Testing what happens if the control room operators walk away?
Maybe testing patience in Abaco? Definitely!

Posted 6 August 2017, 12:43 p.m. Suggest removal

Log in to comment