Utility-scale solar ‘no go’ for Nassau

By NEIL HARTNELL

Tribune Business Editor

nhartnell@tribunemedia.net

Utility-scale renewable energy is “not economically viable” on New Providence, BPL’s former manager ruling out a $140 million solar farm investment in its business plan.

PowerSecure, in its analysis of options to achieve the Government’s renewable energy goals, analysed the feasibility of both a 40 Mega Watt (MW) solar farm for New Providence and the renewable energy self-generation (RESG) programme that Bahamas Power & Light (BPL) has ultimately moved ahead with.

Besides the difficulties associated with finding 155 acres of land for the solar farm, BPL’s business plan said it would be unable to produce energy “when it is needed most” - during the evening hours between 7pm and 11pm, when the darkness coincided with peak loads.

“Because of the cost of the initial investment and other operational factors, the 40 MW solar farm is not an economically viable investment for BPL in the near-term,” PowerSecure argued.

“The total cost of the 155-acre field is $139 million, not accounting for land. The annual operations and maintenance costs are estimated at $0.56 million, not including the cost of spinning reserves. The unit cost is approximately $0.10 per kilowatt hour (KWh), but one developer in Nassau recently quoted $0.19 per KWh factoring in land - furthering the financial challenges.”

BPL’s business plan, though, said the main problem was the inability to align solar energy production with its peak night-time demands.

“Because of the poor coincidence of customer demand versus solar availability, a 40 MW solar installation can provide about 5.6 per cent of BPL’s annual demand requirements, based on the hourly forecast for 2016 - about one-sixth of peak demand,” PowerSecure estimated.

“At BPL’s latitude, solar output has a 24 per cent load capacity and is not firm capacity that can be counted toward peak demand..... Solar power is not available during the hours when it is needed most, between 7pm and 11pm. Moreover, the 40 MW of solar capacity would operate only at a 24 per cent load factor, and therefore would not contribute to BPL’s system peak.”

Some observers are likely to be surprised that PowerSecure ruled out utility-scale solar for New Providence so readily, but the US utility has built up significant expertise and experience in the field.

However, Desmond Bannister, minister of works, acknowledged in a recent Tribune Business interview that the scarcity of suitable land in New Providence was a major impediment to the development of utility-scale solar.

“One of the issues with solar in New Providence is that it simply takes up large areas of land, so we’re going to have to look at green buildings, roof-top installations,” he conceded.

PowerSecure had promised to keep “reevaluating” this and other renewable energy options during the course of its five-year management contract, which was brought to an end after just 18 months.

Apart from problems in securing the necessary land at reasonable price, PowerSecure said the 40 MW solar farm would not allow it to retire its own generation units due to the loss of production whenever there was significant cloud cover.

This meant all its units would have to be kept on stand-by to take over from the solar farm, which it forecast as being able to produce a peak monthly output of 39,401 kilowatts, and 85,497 mega watt hours annually.

The “unstable nature” of BPL’s existing infrastructure presented a further obstacle, and PowerSecure concluded that the 40 MW farm’s value failed to offset the costs of using the existing generation capacity.

“The solar project’s total annualised cost of $8.6 million is less than the savings by a ratio of 1.71,” BPL’s business plan concluded. “Should the cost of ADO fuel (used at Blue Hills) climb to historical highs, as a year ago, then the savings would far exceed costs.

“However, there is consideration of converting generators to use propane or LNG fuel. In a comparison of the avoided cost savings using propane fuel for generation, the annualised cost of the solar project exceeds the avoided cost benefit by a ratio of 1.52.”

The plan recommended: “A solar generating project should not be considered unless there is a determination that the combustion turbines will not be converted to LNG or LPG. Customer solar systems should be encouraged, and should be paid the avoided cost of the fuel they replace.”

Renewables, though, represented a key component of PowerSecure’s plans to slash BPL’s annual Family Island costs of $105.33 million, broken down into $70.73 million associated with fuel and $34.6 million for operations.

“The financial goal is to reduce fuel costs by 15 per cent and operations costs by 32 per cent,” PowerSecure said. “Historically, managing the Family Islands has been a challenge for BEC in terms of cost, service and reliability... Of the 155 MW of generation equipment and plant infrastructure located on the Family Islands, approximately 55 MW are in poor-to-moderate condition, or at beyond-end-of-useful life.

“There is virtually no renewable energy in the Family Islands. Obviously, this represents an excellent opportunity for fuel savings and environmental responsibility.”

Comments

bahamas12345 says...

Overyonder Cay is using solar and windmill for there power.

Posted 26 September 2017, 3:10 p.m. Suggest removal

sealice says...

I think the truth is that the gubmint makes too much money off of taxing and retaxing and Vatting and Revatting to ever honestly say they want to change to green power generation methods.

If they went solar we'd probably get income tax in the same bill....

Posted 26 September 2017, 3:13 p.m. Suggest removal

DDK says...

One acre is approximately 208 square feel. This is about the size of two average sized lots. So if 155 acres is needed this is approximately the size of 416 lots. Must the 155 acres be in one area? Seems a great opportunity to demolished squalid shanty towns and replace them with a much needed source of power. The Family islands obviously have no such land shortage, so perhaps BEC should start with them.

I am not a power generation expert, but the likes of Power Secure are obviously in bed with big oil so I would not trust their logistics and reasoning. In certain parts of the U.S., big oil is so greedy their government has instituted a system of fines for persons using solar panels and attempting to bypass costly and unreliable city power. There are so many permits and hoops persons have to jump through, the idea being to discourage them from moving away from gas and oil consumption.

Posted 26 September 2017, 3:19 p.m. Suggest removal

aconcernedresidentofnassau says...

Just for clarity: 1 acre = 43,560 sq ft - 155 acres X 43,560 / 7500 = 900 average lots (of 7500 sq ft) - it makes more sense for households to receive some incentive for going solar. Just use your own roof area,

Posted 26 September 2017, 4:07 p.m. Suggest removal

DDK says...

My bad, I think I should have said 2 lots worth of space x 155 = 310 lots worth of space. In any event, you are right about using one's own roof. The initial start up cost has come down quite a bit.

Posted 27 September 2017, 2:35 p.m. Suggest removal

sucteeth says...

Wow.. this is why our country is in such bad shape. people uneducated .. 1 acre 208 sqft. lol.. if your going to post a comment at least do your homework first and check the facts.. just saying..

Posted 27 September 2017, 5:56 a.m. Suggest removal

DDK says...

208 x 208 = 43264.00. I DID say approximate. Also assumed most lots were 100 x 100. Speaking of a lack of education..........

Posted 27 September 2017, 1:08 p.m. Suggest removal

sheeprunner12 says...

PowerSecure is out of the picture ........... Next??????????

Posted 26 September 2017, 4:03 p.m. Suggest removal

proudloudandfnm says...

I have always said. We can't afford solar. Just buy some new gennies and bury the power lines. But musdda sick man do something! Lol. Nassau can't keep the electric on for more than 8 hours at a time.. Do something quickly...

Posted 26 September 2017, 6:24 p.m. Suggest removal

The_Oracle says...

Power secure is a typical U.S. utility: Alt energy is subsidized and done to meet federal requirements concurrent with standard steam generation expansion.
You want a 1 Gig steam plant? add 50 Meg in alt energy and the permits will be approved.
The problem however, is the lack of knowledge and ability to think intrinsic in our elected and appointed officials. Surrounded by special interests that make their job easy: do nothing, it won't work can't be done, we don't want it.
Solutions are being developed in spite of Governments and Government owned utilities
throughout the 3rd world.

Posted 26 September 2017, 6:24 p.m. Suggest removal

OldFort2012 says...

Question: why do you need to build it on New Providence? 155 acres in one block is problematic for New Providence, but absolutely nothing for Andros. Just run a cable from there to here.

Posted 27 September 2017, 7:24 a.m. Suggest removal

Log in to comment